The project based on three phases:
Phase I: Design and manufacture of basic and Si-analyser units
- Outline of the X-ray optics of the Multiple-Detector System (08.-09.1998)
- Design of the basic and Si-analyser units with AutoCAD® and manufacture (09.-12.1998)
- First tests of the system at HASYLAB (12.1998)
- Final design, manufacture and tests of the basic and Si-analyser units (01.-03.1999)
- Installation and putting into operation at HASYLAB (06.1999)
Phase II: Extension with Ge Channel-Cut analyser crystals
- Calculation and preparation of the Ge Channel-Cut analyser crystals, design and manufacture of these units (06.-09.1999)
- First tests and results of the Ge Channel-Cut analyser crystals (10.1999)
- Further development, simulation of the routine operation (12.1999-01.2000)
- Development of adjustment technics and tools (04.2000)
- Final test of the Multiple-Detector System and start of the routine operation (05.-06.2000)
Phase III: Documentation, programming, scienfitic report
- Work out of the technical handbook (04.-07.2000) and technical drawings (08.-09.2000)
- Programming and scienfitic report (04.-11.2000)
Links to the project: Science Design Applications Overview Feedback & Info Team Posters Seminars Publications Documentation
MULTIPLE-DETECTOR-SYSTEM
© 2001 Last update 30.04.2001 All photographs taken by W.-H. Kaps. We acknowledge financial support by the BMBF (05SM8VTA39).